Skip to main content
Skip to main content
 

Bankrupt Rd Water District

Bankrupt Road Water District:  When bill are issued Pay online at link below or call 315-455-7061 for additional help. 
Users of the Town's water and sewer districts can pay online at https://www.govpaynow.com/gps/user/plc/a001i7
We cannot receive payments for the Village via this link.  If a Village resident pays through this link, the payment will be rejected.

December 10, 2024:  
  • The Contractor is continuing the testing of the water mains southwest of County Route 6. 
  • We expect te remainder of the services to be installed starting this week along County Route 6, and what restoration that can be completed will be done (weather dependent). 
  • We have the "hookup letters" from OCWA in our possession.  These letters will only be sent out once DOH approval is granted.  
SCHEDULE STATUS:
Schroeppel-Bankrupt Rd (17-0052)  
Continue Construction   Oct, 2024
Commence Canal Boring Setup Oct, 2024
Construction Meeting Oct, 2024
Continue Restorations Oct, 2024
Continue Water Services Oct, 2024
Complete Canal Boring Nov, 2024
Complete Water Distribution Nov, 2024
Project Closeout Q2 /2025

An Engineer's UPDATED SCHEDULE is below as of October 2024.  An engineer's update letter was sent to residents (available below).  

See letter below for information about CONNECTING water to you house.  DO NOT connect to the new water system until you receive correspondence from the Town and/or Town Engineers indicating approval to do so.  Disinfection and testing MUST BE completed and approval given by the NYS Department of Health before the system can be put online and made available to the public.  

A WD Map (pdf) is provided below.  (To zoom in, increase the view (%) and use side and bottom bars to move around map.)


Previously...
A Groundbreakiing Ceremony was held at the Schroeppel Town Building in December 2023.  Construction began in December 2023 and completion is anticipated in Summer/Fall 2024 (weather dependent).     

A public hearing was held on December 20, 2022 to present the updated project costs, as detailed in the letter mailed to property owners in the Water District dated December 7, 2022.  As presented at the public hearing, if a petition to hold another vote was not submitted by January 20, 2023, the project would be awarded to the contractor and materials can be ordered.  Lead times on ductile iron pipe (DIP) were a minimum of 6-9 months.  Based on this, materials won’t be delivered for construction until late summer/early fall 2023. 

December 6, 2022:  The Resolution was passed by the Town Board and a Public Hearing was held on Tuesday, December 20, 2022 at 6:15 pm.  Our Town engineer (C2AE) presented updated information, including grant approval from the December 15, 2022 legislative vote.  

The Town of Schroeppel had a meeting with its engineers and contractor for the project.  Again, due to the increase of materials, the town has submitted an application for additional assistance from the COVID Relief Funds (ARPA) through Oswego County.